Bulk Chemical Mixing Plant

Bulk chemical mixing plant at Southampton Docks

Project overview –Precision Pipework were called to site to design and install suitable equipment to allow Ammonium Nitrate to be mixed and heated to produce a bulk liquid fertilizer. The project included the transfer of the hot product over 200m to a tank storage facility. After the product has cooled and settled it can be transferred into road tankers ready for delivery to surrounding farms.

The tanks were equipped with audio / visual alarms to warn of impending overfill situations. Each tank was fitted with a fail safe air actuated valve which could be remotely switched to prevent the need for operators entering the bunded tank area. The installation took less than 3 months from start to fertilizer production.

Southampton Docks - Completed Feb 1999

Mixer tank

Design , supplied , installed and tested the following:

Mixing tank controls mounted in the boiler room.

Storage tank facility